What specifically has been achieved in the development of Latvenergo WPP (wind power plant) projects?
Latvenergo is continuing the environmental research started in 2022 to develop WPPs, and we also plan to begin studies at several more potential construction sites this year. We have assessed the entire territory of Latvia and identified publicly available constraints for the installation of WPPs. One of the features of Latvia's territory is the large number of farmsteads, as well as a mosaic landscape that is favoured by many protected birds. Accordingly, areas with few or no restrictions are limited. In addition, there are currently no unified guidelines developed at the national regulatory or recommendation level for assessing the impact of WPP projects, which would significantly facilitate processes both during the implementation of research and for the approval of environmental impact reports. To ensure a comprehensive assessment of all aspects, we are conducting a procurement process to select engineering consultants. In parallel, we are holding a pre-procurement consultation phase with major turbine manufacturers. One of the conditions for equipment manufacturers to submit offers is that the project developer must have previously completed a series of 'homework' assignments—that is, they must have obtained the permits that provide the right to commence turbine assembly without obstacles and within a predictable timeframe.
Is the development of WPP projects more complex compared to SPP?
The development of WPP projects is significantly longer compared to SPP (solar power plant) projects because there are a number of constraints that must be taken into account for WPP project implementation, and the set of required measures is different. For example, WPP projects almost always require an environmental impact assessment, unlike SPP projects. An environmental impact assessment is a long and complex process involving, at times, more than 20 different state and municipal institutions, as well as an uncountable number of various stakeholders. Currently, Latvia is in a situation where there is a shortage of environmental experts for EIA assessments—such as ornithologists, habitat experts, or bat experts—because the number of potential WPP projects underway is high. We are looking for solutions to attract experts from other EU countries for field research work, which must be carried out seasonally. However, it should be mentioned that active implementation of wind farms is taking place across the entire EU, and experts are unavailable in Europe generally. A second aspect is that, until now, municipal spatial planning documents have not envisaged structures such as WPPs. In some municipalities, there is a particularly negative attitude towards WPPs, which cannot be said of SPP parks. So far, we have not encountered resistance from municipalities regarding the construction of SPP parks. A third aspect is that WPP projects have a longer period before technical regulations for grid connection can be obtained, as these can only be received after the environmental impact procedure is completed. At the same time, the installation of the connection itself may also require an environmental impact assessment, and, overall, SPP and WPP projects compete with each other for available grid connection capacities.
Electricity Market Overview No. 140